qaafPakistan calculators

House Construction Cost Calculator Pakistan 2026

Cost of building a house from the covered area or the plot size, with per sq ft rates for A, B and C category construction by city and a breakdown of bricks, cement, steel, sand, crush and labour.مکان کی تعمیر کا خرچ
Work out from
marla

1 kanal = 20 marla

%

Blank uses 75%, typical for this plot size

Marla size
Include
Use your own rates
Rs/sq ft

Blank uses the rate for your city and quality

Rs/sq ft

Lahore material rates for the breakdown, as on 26 September 2026. Left unchanged, they are adjusted by the city factor; a rate you type is used as it is.

Rs/bag
Rs/kg
Rs/1000
Rs/cft
Rs/cft
Rs/sq ft
Estimated cost to build10 marla, double storey, Lahore
Rs 2.16 crore
21,600,000Rs
Covered area3,375 sq ft
Plot area2,250 sq ft, 75% covered per floor
Grey structure at Rs 3,200/sq ft10,800,000
Finishing at Rs 3,200/sq ft10,800,000
Average cost per sq ft6,400

Grey structure breakdown (thumb rule quantities)

ItemQuantityCost (Rs)
Bricks67,500 bricks1,350,000
Cement1,350 bags1,957,500
Steel (sarya)11,138 kg2,918,025
Sand6,075 cft486,000
Crush (bajri)4,050 cft526,500
Grey structure labour3,375 sq ft1,518,750
Other grey items and builder's margin2,043,225

Other grey items cover shuttering, plumbing and electric pipes, water, curing, termite proofing and the contractor's margin. Quantities are estimates; your architect's bill of quantities is the final word.

In September 2026 a standard house in Lahore costs about Rs 6,400 per sq ft of covered area to build: Rs 3,200 for the grey structure and Rs 3,200 for finishing. A 10 marla double storey of 3,375 sq ft therefore comes to about Rs 2.16 crore.

Enter your plot size and storeys, or the covered area from your map. Pick the city and the quality of work. The calculator also lists the bricks, cement bags, steel, sand, crush and labour a grey structure of that size needs, priced at this month's market rates. You can type your own contractor's rates under "Use your own rates".

Construction cost per sq ft in Pakistan, 2026

Rates per sq ft of covered area in Lahore. Grey structure is the frame, walls, roof slabs and plumbing and electric pipes. Finishing is plaster, flooring, paint, doors, windows, kitchen, bathrooms and fittings.

QualityGrey structureFinishingComplete
A category (premium)Rs 3,600Rs 5,000Rs 8,600
B category (standard)Rs 3,200Rs 3,200Rs 6,400
C category (economy)Rs 2,800Rs 2,000Rs 4,800

A category means imported or top local fittings, marble or porcelain floors and solid wood. B category is good local brands, porcelain or ceramic tiles and standard wood work. C category is basic tiles and fittings. Rates are from contractor lists published in August and September 2026.

Rates in other cities

Labour and transport change the cost from city to city. These factors are applied to the Lahore rate.

CityFactorB category complete rate
Lahore1.00Rs 6,400/sq ft
Karachi1.02Rs 6,528/sq ft
Islamabad and Rawalpindi1.05Rs 6,720/sq ft
Faisalabad0.94Rs 6,016/sq ft
Multan0.92Rs 5,888/sq ft
Peshawar0.96Rs 6,144/sq ft

Smaller towns are often cheaper on labour but dearer on transport of steel and cement. If your city is not listed, start from the Lahore rate and adjust with local quotes.

Worked example: 10 marla double storey

This is the example loaded above: a 10 marla plot on the 225 sq ft marla, double storey, B category, Lahore.

  1. Plot area: 10 x 225 = 2,250 sq ft.
  2. Covered area: about 75% of the plot on each floor, so 2,250 x 0.75 x 2 = 3,375 sq ft.
  3. Grey structure: 3,375 x Rs 3,200 = Rs 10,800,000.
  4. Finishing: 3,375 x Rs 3,200 = Rs 10,800,000.
  5. Total: Rs 21,600,000, about Rs 2.16 crore.

The grey structure breakdown at the 26 September 2026 rates:

Item Quantity Cost
Bricks at Rs 20,000 per 1,000 67,500 Rs 1,350,000
Cement at Rs 1,450 a bag 1,350 bags Rs 1,957,500
Steel at Rs 262 a kg 11,138 kg Rs 2,918,025
Sand at Rs 80 a cft 6,075 cft Rs 486,000
Crush at Rs 130 a cft 4,050 cft Rs 526,500
Labour at Rs 450 a sq ft 3,375 sq ft Rs 1,518,750

These add up to Rs 8,756,775. The other Rs 2,043,225 of the grey structure covers shuttering, pipes, water, curing and the contractor's margin.

Cost of common plot sizes

Double storey, B category, Lahore rates, 225 sq ft marla, at the typical covered area for each plot size.

PlotCovered areaGrey structureComplete house
3 marla1,148 sq ftRs 36.7 lakhRs 73.4 lakh
5 marla1,913 sq ftRs 61.2 lakhRs 1.22 crore
7 marla2,678 sq ftRs 85.7 lakhRs 1.71 crore
10 marla3,375 sq ftRs 1.08 croreRs 2.16 crore
1 kanal5,400 sq ftRs 1.73 croreRs 3.46 crore

See the detailed pages for a 5 marla house, a 10 marla house and a 1 kanal house.

How the calculator works

Covered area

Cost is charged on covered area, not plot area. Covered area is every floor you build, including stairs and the roof room (mumty), but not open lawns or the car porch roof unless it is enclosed. If you enter a plot size, the calculator assumes a typical share covered on each floor after the front, back and side spaces housing societies require: 85% up to 7 marla, 75% up to 15 marla and 60% for larger plots. Type your own percentage if your map differs.

Rates

Grey structure and finishing rates come from the rate lists in the table above. Change them if your contractor quotes differently. Contractors quote either "with material" or "labour only"; the rates here are with material.

Material quantities

The breakdown uses thumb rules per sq ft of covered area for an RCC framed house with 9 inch outer walls: 20 bricks, 0.4 bags of cement, 3.3 kg of steel, 1.8 cft of sand and 1.2 cft of crush. Basements, raft foundations or long spans need more steel and concrete. For a single wall or slab, use the brick calculator or the concrete calculator.

These are planning figures, not a quote. Soil, design, basement, boundary wall, underground tank and approvals can add 10% or more. Get a bill of quantities from your architect and at least two contractor quotes before you start. Material prices move every week; the rates here are dated in the form.

Construction cost questions

What is the construction cost per square foot in Pakistan?

About Rs 6,400 a sq ft for a standard B category house in Lahore in September 2026, of which Rs 3,200 is grey structure. Economy work is about Rs 4,800 a sq ft and premium about Rs 8,600. Islamabad is about 5% higher and Multan about 8% lower.

What is the grey structure rate per sq ft in 2026?

Between Rs 2,800 and Rs 3,600 a sq ft with material in Lahore, depending on quality. That covers foundations, columns, beams, slabs, brick walls, and the pipes and conduits inside the walls. Plaster is usually counted in finishing, so check what your contractor includes.

How much does it cost to build a 5 marla house in 2026?

About Rs 1.22 crore for a double storey of 1,913 sq ft at B category Lahore rates, or Rs 61 lakh for a single storey. Premium finishing takes the double storey to about Rs 1.64 crore. The 5 marla page shows the full breakdown.

How many bricks are needed for a house?

About 20 bricks per sq ft of covered area for a framed house with 9 inch outer walls. A 10 marla double storey of 3,375 sq ft needs about 67,500 bricks. Load bearing houses with no RCC frame use more. For one wall, the brick calculator gives an exact count.

Is labour included in the per sq ft rate?

Yes. The rates are "with material" rates that include materials, labour and the contractor's margin. Labour only contracts for grey structure were about Rs 400 to Rs 450 a sq ft in mid 2026. If you buy materials yourself, add the labour rate to your own material costs.

Related tools

Sources: Contractor rate lists for Lahore published in July to September 2026 (grey structure Rs 3,000 to 3,600 a sq ft; economy, standard and premium grey and finishing rates; a 10 marla bill of quantities); cement and steel dealer rates reported on 26 September 2026; Lahore brick kiln rates of 25 September 2026. Thumb rule quantities are the middle of published 2025-26 Pakistani estimates. All rates are in the site's data file and are updated monthly.

Last reviewed 30 September 2026. Results are estimates; official notices always take precedence.